Scope of works
The project entailed a comprehensive removal of 64 aged Colt AOV roof vents throughout the building, which were then replaced by 64 new AOVs, inclusive of associated wiring, control panels, and sensors.
To ensure minimal disruption to the regular operations of the bank headquarters, all activities were carried out outside regular working hours.
Furthermore, the removal and renewal of the fire system was conducted in phases, with the old and new systems functioning concurrently.
This strategic approach guaranteed that the building’s fire safety plan remained operational at all times.